One of the most expensive assumptions in borehole drilling is that a rig which performed successfully on the previous project will deliver similar results at the next site.
It is an understandable assumption, particularly for contractors working under tight mobilisation budgets and project schedules. A familiar rig, an established crew and readily available equipment can make mobilisation faster and appear to reduce operational risk. Yet the geological conditions encountered underground may be very different from those at the previous site.
The problem is particularly relevant in Kenya, where groundwater occurs in a variety of geological environments, including volcanic formations, weathered basement rocks, fractured crystalline rocks, alluvial deposits and sedimentary aquifers. A drilling method suited to one environment may be inefficient or unsuitable in another.
Down-the-hole (DTH) hammer drilling is widely used in hard and competent rock, while conventional mud rotary drilling is commonly applied in unconsolidated sediments and softer formations. Both methods have distinct advantages. However, selecting between them requires an understanding of the entire geological sequence, the intended borehole design and the equipment needed to complete the well.
The mistake is often made before mobilisation: selecting equipment based on what worked previously rather than what the new borehole is likely to encounter.
Drilling in volcanic formations: The importance of impact energy and air supply
Much of Kenya’s Rift Valley and the surrounding volcanic terrains are characterised by sequences of basalt, trachyte, tuff, volcanic breccia and other volcanic deposits. These formations can present demanding drilling conditions because of their hardness, abrasiveness, variability and the presence of fractures.
DTH hammer drilling is particularly effective in competent hard rock. The hammer is positioned immediately above the drill bit, where compressed air drives an internal piston that repeatedly strikes the bit. The resulting impact fractures the rock, while rotation allows the cutting elements to engage fresh surfaces.
Unlike conventional rotary drilling, where the cutting action is primarily generated through rotation and weight on the bit, DTH drilling delivers percussion energy close to the rock face. This makes it effective in formations where conventional rotary bits may experience slow penetration and excessive wear.
However, successful DTH drilling depends on two closely related operating requirements: sufficient air pressure to operate the hammer and sufficient air volume to remove the resulting cuttings.
Compressed air travels down the drill string, operates the hammer and exits through the bit. The exhausted air then carries rock fragments upwards through the annular space between the drill pipe and the borehole wall.
This means the same air supply performs two functions. The compressor must provide the hammer’s required air consumption at the necessary operating pressure while also maintaining sufficient return velocity to transport cuttings out of the hole.
This relationship becomes increasingly important as borehole diameter increases.
A larger borehole creates a larger annular space, requiring more air volume to maintain an effective upward velocity. If the air supply is inadequate, cuttings may accumulate around the bit, become repeatedly crushed and increase friction and drilling resistance. The resulting symptoms may be mistaken for poor rock penetration or an underperforming hammer when the underlying problem is inadequate hole cleaning.
Compressor selection must consequently consider the hammer manufacturer’s air consumption specifications, operating pressure, borehole and drill-string dimensions, drilling depth, pressure losses and actual compressor delivery under site conditions.
The distinction between compressor free-air delivery and the compressed air’s actual volume inside the borehole is also important when carrying out these calculations. A theoretical flow requirement derived from annular area and target velocity cannot be compared directly with a compressor’s rated free-air delivery without accounting for pressure and temperature conditions.
For contractors, the implication is clear: selecting a compressor solely from the hammer’s nominal air consumption can result in an inadequate drilling package.
The sedimentary challenge: Cuttings removal and borehole stability
The engineering requirements change considerably when drilling through unconsolidated or poorly consolidated materials.
Alluvial deposits, sands, silts, clays and some sedimentary formations are often less competent than volcanic bedrock. The main challenge is not necessarily breaking the formation but maintaining borehole stability while continuously removing the material generated during drilling.
Mud rotary drilling addresses these requirements through the circulation of drilling fluid, commonly water-based bentonite or polymer-based mud.
A mud pump sends the drilling fluid down the drill pipe and through the bit. The fluid returns to the surface through the annular space, carrying cuttings into settling pits or a solids-control system.
The drilling fluid performs several functions. It transports cuttings, helps support the borehole walls, cools and lubricates the drilling bit, reduces friction and can help control the entry of groundwater into the borehole.
Its properties must be monitored throughout drilling. Mud that is too thin may not provide sufficient support or cuttings transport, while excessive viscosity or density can increase pumping resistance, complicate solids separation and contribute to drill-string sticking.
This requires more than a rig with adequate lifting capacity and a rotary head. A properly equipped mud rotary operation needs a suitable mud pump, mixing facilities, circulation tanks or pits, drill pipes, fluid preparation materials and arrangements for managing drilling returns.
Water availability is another operational consideration, particularly in Kenya’s arid and semi-arid regions. Contractors must plan for the initial preparation of drilling fluid, replenishment during drilling and losses into permeable formations. Where water is unavailable at the site, transportation can become a significant component of the drilling budget.
A contractor who prices the drilling operation without accounting for water supply, mud additives, circulation equipment and fluid losses may find that an apparently competitive contract becomes increasingly expensive during execution.
The difficult ground is often between the two formations
The assumption that a borehole will remain within one geological formation from the surface to its final depth is another source of operational difficulty.
A site may begin with loose soil and weathered material, pass through laterite or cemented gravel, and eventually encounter hard volcanic rock. Elsewhere, a borehole may cross alternating layers of clay, sand, gravel and fractured rock.
These transitions can make a single drilling method inefficient.
DTH hammer drilling performs well in competent rock but may be unsuitable for loose overburden without appropriate casing or other stabilisation measures. Unconsolidated materials can collapse into the hole, while water-bearing formations may introduce additional challenges for air circulation.
Mud rotary drilling can manage many of these softer materials, but penetration through hard, abrasive rock may be slow and can increase bit wear and operating costs.
A practical solution is to use a rig and drilling arrangement capable of accommodating more than one method.
The Japan International Cooperation Agency’s Technical Manual for Drilling Works describes a staged approach to drilling in hard-rock environments. Where unconsolidated overburden overlies competent rock, the upper section may first be drilled using mud circulation, after which conductor casing is installed before DTH drilling continues into the harder formation.
This is an important consideration for Kenyan contractors. The most suitable equipment may not be a rig dedicated exclusively to either method, but one capable of handling the geological transition while maintaining the required borehole diameter and construction standards.
The Water Resources Authority’s January 2026 procurement specifications for exploratory boreholes in Garissa County provide a local example. The specifications require drilling equipment with air and water/mud flushing facilities, alongside DTH hammer capability for hard rock. They also identify direct mud circulation for softer formations and DTH drilling for hard formations.
The same procurement document recognises that actual geological conditions encountered during drilling may differ from the preliminary description. This reinforces the need for equipment flexibility and adequate site investigation.
The drilling method also determines how the borehole is completed
The selection of a drilling method should not end with the question of how quickly a particular formation can be penetrated. It must also account for the construction of the completed borehole.
In unconsolidated sedimentary aquifers, casing and screen design are critical. The screen must be positioned across the intended water-bearing interval, with an appropriate gravel pack where required to limit the entry of formation particles while allowing groundwater to flow into the well.
The borehole may also require sealing and grouting to prevent the movement of contaminated surface water or groundwater between different geological layers.
In fractured-rock aquifers, the approach can be different. Groundwater may enter through discrete fractures rather than a continuous granular aquifer. Depending on the hydrogeological assessment, sections of the borehole may be cased while water-bearing fractures are left open for production.
These differences affect the required drilling diameter, casing programme, drilling tools and final borehole configuration.
Borehole development is equally important. After drilling and installation of the permanent casing and screen, the well must be cleaned to remove drilling fluids, fine particles and accumulated cuttings. Development may involve airlifting, surging, pumping or other appropriate techniques.
A pumping test is then required to assess the borehole’s performance, including its yield, drawdown and recovery characteristics. Water quality testing is also necessary before the water is put to its intended use.
A borehole that has been drilled quickly but is poorly developed, inadequately screened or improperly sealed may become a costly long-term failure.
Geological intelligence should precede equipment mobilisation
A geological map is a useful starting point, but it is not a substitute for site-specific hydrogeological information and records of completed boreholes.
Before selecting a drilling method, contractors and project engineers should seek information from several sources.
Existing borehole completion records: Records from nearby boreholes can provide information about the geological sequence, depth of water-bearing formations, casing intervals, static water levels, final borehole diameter and pumping-test results. The Water Resources Authority and relevant county water offices are important sources of groundwater information.
Previous drilling performance: The method used on neighbouring boreholes, penetration rates, depths at which formation changes occurred, problems encountered and the equipment deployed can help inform the drilling plan.
Aquifer characteristics: The distinction between fractured-rock and granular aquifers influences borehole design and completion. In fractured rock, the objective may be to intersect productive water-bearing fractures. In sedimentary formations, the design must account for the thickness and characteristics of the aquifer, screen placement and appropriate gravel packing.
Potential drilling problems: Historical information about borehole collapse, excessive sand production, loss of drilling fluid, stuck drill strings and unsuccessful wells can reveal risks that may not be apparent from regional geological mapping.
Site logistics: Access roads, water availability, fuel supply, space for drilling equipment and circulation pits, proximity to settlements and the availability of spare parts should all be considered before mobilisation.
The investigation should also include an assessment of the proposed drilling depth, required borehole diameter and anticipated casing programme. These parameters directly affect equipment selection and operating costs.
The economics of selecting the wrong rig
The financial implications of poor equipment selection extend beyond the cost of hiring a drilling rig.
Inadequate air supply can reduce penetration rates and increase bit wear. Poor mud circulation can lead to hole instability, stuck drill strings and additional time spent cleaning the borehole. Insufficient lifting capacity can restrict the depth or casing programme that a contractor can safely execute.
Other costs include additional mobilisation, water transportation, fuel, replacement drilling tools, lost circulation materials and the possible need to ream or redrill sections of the borehole.
The commercial implications are particularly significant where contracts are priced per metre drilled or include fixed completion deadlines. A contractor who underestimates geological uncertainty may find that the original cost assumptions no longer hold once drilling begins.
For project owners, the lowest mobilisation price is not necessarily the lowest-cost option. Equipment suitability, drilling experience, contingency arrangements and the contractor’s ability to complete the borehole to the required specification should form part of the procurement assessment.
A more disciplined approach to drilling decisions
The choice between DTH and mud rotary drilling should be based on an integrated assessment of geology, hydrogeology, borehole design and site logistics.
Before mobilisation, contractors and project engineers should:
- Review nearby borehole completion records and available hydrogeological investigations rather than relying exclusively on regional geological maps.
- Establish the expected geological sequence, including the depth and nature of unconsolidated overburden, cemented layers, fractured rock and productive aquifers.
- Match the drilling method, bit, drill string, compressor or mud pump to the proposed borehole diameter and depth.
- For DTH operations, verify hammer air consumption, operating pressure, compressor free-air delivery and the air volume needed for effective cuttings removal under actual operating conditions.
- For mud rotary operations, provide adequately sized pumps, mixing and circulation facilities, and budget for water, additives and management of drilling fluids.
- Provide for changes in drilling method where geological transitions are anticipated, including suitable casing and stabilisation arrangements.
- Assess the complete borehole construction programme, including casing, screens, gravel packing, sealing, development, pumping tests and water quality analysis.
- Evaluate contractors on their ability to deliver a completed and functional borehole, rather than on rig availability or quoted drilling rates alone.
Kenya’s groundwater development framework already recognises the importance of proper investigation, construction and supervision. The Water Resources Authority, working with the Ministry responsible for water, has developed separate codes of practice covering borehole siting, construction, supervision and pumping tests. Their application is intended to reduce borehole failure and support sustainable groundwater development.
The wider lesson for the drilling industry is that equipment selection is an engineering decision, not an administrative convenience.
A rig that performed well in one geological environment is not automatically the right rig for another. The best drilling operation begins with an understanding of what lies beneath the site, the water resource being targeted and the technical requirements of the completed well.
The difference between a successful borehole and an expensive drilling exercise may be determined long before the first drill pipe enters the ground.