Last Updated 14 years ago by Kenya Engineer

As part of the Government’s efforts to promote clean and renewable energy development in Kenya, the Geothermal Development Company (GDC) Ltd is seeking registration and development of its geothermal projects under the Clean Development Mechanism (CDM) of the Kyoto Protocol, United Nations Framework Convention on Climate Change.

The ultimate objective of these projects is contribution towards national sustainable development and increased electricity generation towards attainment of Kenya’s vision 2030. Additionally, the geothermal projects will target the abatement of carbon dioxide (CO2) from generators on the Kenya interconnected electricity grid. This abatement will be achieved by reducing the need for new thermal power plants in Kenya as well as decreasing the dependence of Kenya on imports of crude petroleum (accounting for 20-25% of the national import bill). In particular diesel, a common fuel source of recent power plant developments in Kenya.

Three projects are currently at the PDD stage for CDM registration by 2013 having received Letters of No Objection from the National Environment Management Authority (Designated National Authority):

1.    1. 1200MWe Menengai geothermal power project
The project is currently at the Exploration stage. The power plant covered under the CDM will be developed in three phases over thirty months with; 2x100MWe installed mid-2017, an additional 2 x 100MWe by the end of 2017 and 4x200MWe plants by the end of 2019. It is anticipated that CERs/VERs will be generated and the crediting period will start from the first 200MWe installation mid-2017, with a seven-year crediting period that can be renewed two times for a total crediting period of twenty-one years. The project is expected to reduce an estimated 4,793,000 tCO2-eq per year upon implementation.

 2. 800MWe Bogoria – Silali geothermal power projects
The project is currently at the project preparation stage with an objective of developing the field to a capacity of 800MWe by 2022. Development of the field will be staged in 4 phases with annual 200MWe installations from the year 2019 to 2022 bringing the field capacity up to 800MWe. It is anticipated that CERs/VERs will be generated from the start of operation in 2019, with a seven-year crediting period that can be renewed two times for a total crediting period of twenty one years. An estimated 3,196,000 tCO2-eq per year will be displaced upon project implementation.

1.    3. 50-100MWe Menengai Modular Power Plants

The aim of this CDM project is to develop a capacity of 50-100MWe phased over a period of five years in 5-10MW units between 2013 and 2017. The aggregate CDM project capacity of all the modular power plant units will be in the range 50-100MWe with a seven-year crediting period that can be renewed two times for a total crediting period of twenty-one years. It is expected that CERs/VERs will be generated from the start of operation in 2013. Emission reductions are estimated at 299,600 tCO2-eq per year.

Source:GDC