Last Updated 14 years ago by Kenya Engineer
Kenya’s main power producer, KenGen will today be switching on a 24 mega watt hydropower unit at Kindaruma power station. The station with two installed units had switched off one of the units for upgrading and repair works last year in June. It will now generate 24 mega watts, 20 per cent more power than the 20 megawatts it produced before.
The plant located 170 km NE of Nairobi was originally designed with a provision of three turbine generator units but only two vertical Kaplan turbines were installed. The company however intends to add a third unit, a move that will almost double Kindaruma’s output from 40MW in 2011 to 72 by end of this year.
Kindaruma’s first unit was commissioned in 1968 making it the first major power station in constructed in the Seven Forks complex and the last unit commissioned in 1968.Power from Kindaruma is transmitted directly to Nairobi or to Kamburu via a 132KV substation.
Other hydropower stations in the country are Gitaru, has 3 units with a design capacity of 225 MWe; Kiambere, has 2 units with a with a design capacity of 168 MW; Kamburu, has 3 units with a a design capacity of 94.2 MW; Masinga, has 2 units with a design capacity of 40 MW; Sondu Miriu, has 2 units with a design capacity of 60 MW and Turkwel has a design capacity of 106 MW with 4 units installed currently.